The Vermont System Planning Committee – VSPC – is a collaborative process, established in 2007, for addressing electric grid reliability planning. Its purpose is to ensure all options to solve grid reliability issues get full, fair and timely consideration, and the most cost-effective solution gets chosen, whether it is a poles-and-wires upgrade, energy efficiency, demand response, generation, or a hybrid.

Timeline

  1. VELCO Files Permit Application

    VELCO files permit application with PUC for Northwest Reliability Project (NRP), 63-mile upgrade from West Rutland to South Burlington.

  2. Certificate of Public Good Issued

    PUC issues Certificate of Public Good for NRP, stating its intention to open a separate docket to consider how to more fully integrate consideration of non-transmission alternatives into grid planning.

  3. Act 61 Enacted

    Act 61, 2005 VT General Assembly, enacted, amending 30 V.S.A. § 218c to require VELCO to prepare a transmission system plan, after public hearings and opportunity for input by the distribution utilities, the state's Energy Efficiency Utility, and the Vermont Department of Public Service.

  4. Docket 7081 Opened

    PUC opens Docket 7081, Investigation into Least-Cost Integrated Resource Planning for Vermont Electric Power Company, Inc.'s Transmission System.

  5. Memorandum of Understanding Settled

    Following more than a year of negotiation, Memorandum of Understanding settling issues in Docket 7081 submitted by most parties (VELCO, most utilities, Public Service Department, Associated Industries of VT). MOU details VSPC process.

  6. PUC Approves MOU

    Following hearings and other steps in litigation, PUC approves parties’ MOU in Docket 7081 with minor modifications.

  7. VSPC Convenes

    VSPC convenes for the first time. Establishes quarterly meeting schedule.

  8. Forecast zones defined

    Forecast zones defined by VSPC for Vermont load forecasting.

  9. Screening tool adopted

    Screening tool adopted and submitted to PUC for determining which reliability issues require full analysis of their potential to be resolved with non-transmission alternatives.

  10. Non-disclosure agreement adopted

    Form of non-disclosure agreement for critical energy infrastructure information adopted and submitted to PUC.

  11. January - June 2009: Docket 7081 First Cycle

    First cycle under Docket 7081 process for VSPC input into VELCO’s three-year update of 20-year Vermont Long-Range Transmission Plan. After a VSPC draft and input, and a public draft and input, VELCO submits Plan July 1, 2009.

  12. First commercial wind to directly connect to transmission system

    Central Vermont Non-Transmission Alternatives Study Group formed by utilities, led by GMP, to consider whether a transmission project to resolve the Central VT reliability deficiency identified by ISO-New England could be avoided with some combination of generation and demand-side management.

  13. January - June 2012: Docket 7081 Second Cycle

    Second cycle under Docket 7081 process for VSPC input into VELCO’s three-year update of 20-year Vermont Long-Range Transmission Plan. After a VSPC draft and input, and a public draft and input, VELCO submits Plan July 1, 2012.

  14. Central VT NTA Study Group Report

    Central VT NTA Study Group reports findings to ISO-New England that distributed generation and energy efficiency are closing the reliability gap for the Central VT reliability issue.

  15. ISO- New England Findings

    Following re-study, ISO-New England concludes that Central VT deficiency does not arise within their 10-year planning horizon; removes upgrade from Regional System Plan, avoiding a $157 million transmission upgrade.

  16. January - June 2015: Docket 7081 Third Cycle

    Third cycle under Docket 7081 process for VSPC input into VELCO's three-year update of 20-year Vermont Long-Range Transmission Plan. After a VSPC draft and input, and a public draft and input, VELCO submits Plan July 1, 2015. 

  17. January - June 2018: Docket 7081 Fourth Cycle

    Fourth cycle under Docket 7081 process for VSPC input into VELCO’s three-year update of 20-year Vermont Long-Range Transmission Plan. After a VSPC draft and input, and public draft and input, VELCO submits Plan July 1, 2018. 

  18. January - June 2021: Docket 7081 Fifth Cycle
  19. Public Utility Commission

    Public Utility Commission issued memorandum directing VELCO to address specific areas in the next Long-Range Transmission Plan including greater visibility into asset condition project queue, right-sizing opportunities, whether new grid enhancing technologies could defer grid buildouts, whether more storm hardening projects are warranted, and how VELCO’s Plan will align with the goals, objectives, and requirements of the Environmental Justice Act. 

Image
VSPC subcommittees
Subcommittees

All materials associated with the standing and ad hoc subcommittees of the VSPC are posted to the Subcommittees Meeting Library.

Image
VSPC Document Library
Library

Reports, correspondence and filings related to the VSPC process and related reliability-related matters are posted to the Library. 

Image
VSPC Get Involved
Get Involved

Learn about ways to get involved with the Vermont System Planning Committee or learn more about transmission planning.

Image
VSPC Calendar
Calendar

A full listing of VSPC meetings and meeting materials is available on the VSPC calendar.